Wastewater Treatment Works Upgrade: Scope and Delivery Transformation
A major wastewater treatment works upgrade transformed from over budget and behind schedule to £9.3 million under budget and 8 months ahead of programme, meeting the regulatory deadline that the original approach would have missed.
Regulatory Compliance Programme: Modular Delivery
A multi-site regulatory compliance programme delivered with £15.8 million in savings against the original cost envelope, with programme duration reduced by over two years through modular solutions and a restructured delivery model.